Наверх

Transneft Siberia receives positive Glavgosexpertiza conclusion for reconstruction of the Surgut–Polotsk oil pipeline’s line portion

Date of publication: 14 June 2018 Print

Transneft Siberia has received a positive opinion of the Main Department of State Expertise (Glavgosexpertiza) of Russia in relation to project documentation concerning reconstruction of the Surgut–Polotsk oil trunk pipeline (OTP) (from 729th km to 750th km).

According to the project, 20 km of line portion of the Surgut–Polotsk OTP with a diameter of 1,200 mm will be replaced. The pipe will be laid in a new trench with subsequent connection to the operating oil pipeline.

Production facilities will be reconstructed in accordance with the Company's development programme. The main objective is to ensure reliability and environmental safety of Transneft Siberia's oil trunk pipeline system facilities.